Creating a Task Baseline
Creating Task Baselines A task baseline can be created using the default constructor for the TaskBaseLine class as shown below.
This is demonstrated by the following Java Code
1// For complete examples and data files, please go to https://github.com/aspose-tasks/Aspose.Tasks-for-Java
2// The path to the documents directory.
3String dataDir = Utils.getDataDir(CreatingATaskBaseline.class);
4
5Project project = new Project();
6
7// Creating TaskBaseline:
8Task task = project.getRootTask().getChildren().add("Task");
9// set baseline for specified tasks
10List<Task> myList = new ArrayList<Task>();
11project.setBaseline(BaselineType.Baseline, (Iterable<Task>) myList);
12// or set baseline for the entire project
13project.setBaseline(BaselineType.Baseline);