Managing Assignment Cost

Managing Assignment Cost

The ResourceAssignment class exposes several properties used to manage assignment cost:

  • Cost represents an assignment’s total project cost (decimal).
  • BCWP represents the budgeted cost of work to date on an assignment (double).
  • BCWS represents the budgeted cost of work scheduled for an assignment (double).
  • ACWP represents the actual cost of the work carried out on an assignment to date (double).

To view assignment costs in Microsoft Project:

  1. On the Task Usage page, select the Insert menu and then Column.
  2. Add columns.

Resource cost columns in Microsoft Project

modify resource costs in Microsoft Project 2010

Getting Assignment Costs with Aspose.Tasks

The following example shows getting task costs using Aspose.Tasks.