Editing Task Baseline Durations in Ruby

Aspose.Tasks - Task Baseline Duration

To get Task Baseline Duration using Aspose.Tasks Java for Ruby, simply invoke TaskBaselineDuration module. Here you can see example code.

Ruby Code

 1oneSecond = 10000000
 2
 3oneMinute = 60 * oneSecond
 4
 5oneHour = 60 * oneMinute
 6
 7project = Rjb::import('com.aspose.tasks.Project').new
 8
 9task = project.getRootTask().getChildren().add("Task")
10
11project.setBaseline(Rjb::import('com.aspose.tasks.BaselineType').Baseline)
12
13baseline = task.getBaselines().toList().get(0)
14
15duration = baseline.getDuration().toDouble()
16
17baseline_duration = duration / oneHour
18
19puts baseline_duration