Baseline Task Scheduling

In project management, a baseline schedule defines the original planned Start and Finish dates for tasks. By comparing baseline dates with the actual or current schedule, project managers can identify delays, track progress, and evaluate schedule performance. Using the TaskBaseline class in Aspose.Tasks for .NET, developers can programmatically access and manipulate these dates when working with MPP/XML files.

Baseline Start and Finish Properties

The following properties are available:

Both properties use the DateTime data type.

Viewing Baseline Schedule in Microsoft Project

To verify baseline schedule values in Microsoft Project:

  1. From the View menu, select More Views ? Task Entry.
  2. From the Insert menu, select Columns.
  3. Add the Baseline Start and Baseline Finish columns.

checking start/finish dates in Microsoft Project

Getting Task Baseline Schedule using Aspose.Tasks

The code below displays the task baseline schedule in a console window after traversing a task’s baselines.

 1Project project = new Project();
 2
 3// Creating TaskBaseline
 4Task task = project.RootTask.Children.Add("Task");
 5project.SetBaseline(BaselineType.Baseline);
 6
 7// Display task baseline schedule
 8TaskBaseline baseline = task.Baselines.ToList()[0];
 9Console.WriteLine("Baseline duration is 1 day: {0}", baseline.Duration.ToString().Equals("1 day"));
10Console.WriteLine("BaselineStart is same as Task Start: {0}", baseline.Start.Equals(task.Get(Tsk.Start)));
11Console.WriteLine("BaselineFinish is same as Task Finish: {0}", baseline.Finish.Equals(task.Get(Tsk.Finish)));

EUpdating Task Baseline Dates

You can also programmatically set or update baseline start and finish dates:

 1    var project = new Project("input.mpp");
 2
 3    // Access a task
 4    Task task = project.RootTask.Children.GetById(1);
 5
 6    // Get first baseline
 7    TaskBaseline baseline = task.Baselines[0];
 8
 9    // Update baseline dates
10    baseline.Start = new DateTime(2025, 10, 1, 9, 0, 0);
11    baseline.Finish = new DateTime(2025, 10, 5, 18, 0, 0);
12
13    project.Save("output.mpp", SaveFileFormat.Mpp);

Best Practices

Conclusion

Baseline task scheduling is essential for tracking whether tasks are completed on time. With Aspose.Tasks for .NET, you can access and update baseline Start and Finish dates, automate variance analysis, and integrate schedule tracking into custom project management workflows.

Subscribe to Aspose Product Updates

Get monthly newsletters & offers directly delivered to your mailbox.