Creating Task Baseline

Overview

A baseline in project management is a fixed reference point that captures the original planned schedule, cost, and work. By saving a baseline, project managers can later compare it with the actual progress to evaluate project performance and detect variances. Using Aspose.Tasks for .NET, developers can programmatically create task-level baselines or project-level baselines in MPP/XML files without Microsoft Project installed.

When to Create a Task Baseline

Typical scenarios include:

Working with Baselines in Aspose.Tasks

Creating a Task Baseline

A task baseline can be created using the default constructor for the TaskBaseLine class as shown below.

1Project project = new Project();
2
3// Creating TaskBaseline:
4Task task = project.RootTask.Children.Add("Task");
5
6// Set baseline for specified tasks and entire project
7project.SetBaseline(BaselineType.Baseline, new Task[] { task });
8project.SetBaseline(BaselineType.Baseline);

Best Practices

Conclusion

Creating baselines is a fundamental step in project management that ensures reliable performance tracking. With Aspose.Tasks for .NET, you can easily set baselines for tasks or entire projects programmatically, automate scheduling processes, and integrate this functionality into enterprise project management solutions.