Percentage Complete Calculations

Microsoft Project shows the percentage of a task that’s been completed. The percentage can be added manually, by a project manager, or automatically calculated by the application. Aspose.Tasks for .NET supports several percentage calculations related to tasks.

Percentages

The Tsk class exposes a number of properties used to calculate percentages:

To see the physical percent complete in Microsoft Project:

  1. On the Task Entry form, from the Insert menu, select Column.
  2. Add the column.

To see the completed percentage in Microsoft Project one can double-click the desired column in the Task Entry form.

Getting Percentages in Aspose.Tasks

The following example shows how to get the percentages of work relating to tasks using Aspose.Tasks.