Resource Baseline Data
Aspose.Tasks for .NET provides access to resource baseline data in Microsoft Project files. This includes reading and writing baseline cost, work, and timephased data for resources. Both XML and MPP formats are supported. The level of support is consistent across Microsoft Project versions from 2003 to 2021. The table below outlines the availability of each property per format and version.
Number | Property name | XML | MPP | ** | ** | ** | ** | ** | ** | Comments |
---|---|---|---|---|---|---|---|---|---|---|
2003 | 2007 | 2010 | 2013 | 2016 | 2019 | 2021 | ||||
1. | TimephasedData | R/W | R/W | R/W | R/W | R/W | R/W | R/W | R/W | |
2. | Number | R/W | R | R | R | R | R | R | R | |
3. | Work | R/W | R/W | R/W | R/W | R/W | R/W | R/W | R/W | |
4. | Cost | R/W | R/W | R/W | R/W | R/W | R/W | R/W | R/W | |
5. | BCWS | R/W | – | – | – | – | – | – | – | |
6. | BCWP | R/W | – | – | – | – | – | – | – |